Answer:
You would need 24 workers
I am assuming a constant rate
Explanation:
Rate x builders x hours x days = 1 job
Rate: 1 job can be done with 20 builders x 8 hours x 30 days

x builders x 10 hours x 20 days = 1 job
= 1
= 1 Multiple both sides by 24
b = 24
You will need 24 builders.