The last step in project risk management is deciding how to address the knowledge area for a particular project by performing risk management planning.

a. True
b. False

User Adil Saju
by
8.9k points

1 Answer

2 votes
B. False
Explanation: The first step in project risk management is deciding how to address this knowledge area for a particular project by performing risk management planning.