Answer:
$71,900
Step-by-step explanation:
Calculation to determine The cost of jobs transferred to finished goods
Work in Process Inventory Beginning
Add WIP 6,000
Add Direct materials 48,600
Add Direct labor 31,100
Add Applied overhead 17,300
Less Ending WIP 31,100
FINISHED GOODS $71,900
Therefore The cost of jobs transferred to finished goods is: $71,900