Answer:
$34,200
Step-by-step explanation:
Calculation to determine what June's direct material flexible-budget variance is
Flexible-budget variance = (2,400 × $93) − (21,000 × 0.1 × $90)
Flexible-budget variance =$223,200-$189,000
Flexible-budget variance =$34,200 U