15.9k views
5 votes
Are required to complete the work in ays! 12 workers can complete a piece of work in 20 days. How many workers are needed to complete the work in 16

days?​

User Morez
by
7.5k points

1 Answer

6 votes

Answer:

The answer is 15 workers are needed to complete the work in 16 days.

Explanation:
To this incomplete sentence. ill try to answer it

  • To find the number of workers needed to complete a piece of work in 16 days, we can use the formula w = (12*20)/16, where w is the number of workers needed and 12 and 20 are the number of workers and the number of days it takes them to complete the work, respectively.
  • Plugging these values into the formula, we get w = (12*20)/16 = 15.
  • Therefore, 15 workers are needed to complete the work in 16 days.
User McArthey
by
6.6k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.