15.9k views
5 votes
Are required to complete the work in ays! 12 workers can complete a piece of work in 20 days. How many workers are needed to complete the work in 16

days?​

User Morez
by
3.3k points

1 Answer

6 votes

Answer:

The answer is 15 workers are needed to complete the work in 16 days.

Explanation:
To this incomplete sentence. ill try to answer it

  • To find the number of workers needed to complete a piece of work in 16 days, we can use the formula w = (12*20)/16, where w is the number of workers needed and 12 and 20 are the number of workers and the number of days it takes them to complete the work, respectively.
  • Plugging these values into the formula, we get w = (12*20)/16 = 15.
  • Therefore, 15 workers are needed to complete the work in 16 days.
User McArthey
by
3.0k points