Answer:
The answer is 15 workers are needed to complete the work in 16 days.
Explanation:
To this incomplete sentence. ill try to answer it
- To find the number of workers needed to complete a piece of work in 16 days, we can use the formula w = (12*20)/16, where w is the number of workers needed and 12 and 20 are the number of workers and the number of days it takes them to complete the work, respectively.
- Plugging these values into the formula, we get w = (12*20)/16 = 15.
- Therefore, 15 workers are needed to complete the work in 16 days.