Answer:
≈ 53 seconds
Step-by-step explanation:
calculate Time required for the product to begin the falling-rate drying period
Initial moisture content = 0.77 kg water /kg of product
= 3.35 kg water /kg solids
Critical moisture content = 0.3 kg water / kg product
= 0.43 kg water / kg solids
∴ amount of water to be removed = 3.35 - 0.43 = 2.95kg water /kg solids
next: calculate surface are a of product during drying
= (0.05 * 0.05 ) * 6
= 0.015 m^3
Drying rate = 0.1 kg water m^2.s^-1 * 0.015 m^3 = 1.5 * 10^-3 kg water s^-1
applying product density
initial product mass = 0.11875 * 0.23 = 0.0273kg solid
hence total amount of water to removed = 2.92 * 0.0273 = 0.07972 kg
therefore : Time required for the product to begin the falling-rate drying period
= 0.07972 / 1.5 * 10^-3
= 53 seconds