A process with no beginning work in process, completed and transferred out 84300 units during a period and had 50300 units in the ending work in process inventory that were 20% complete. The equivalent units of production for the period for conversion costs were:

User Carlo Wood
by
2.8k points

1 Answer

12 votes
12 votes

Answer:

$94,360

Step-by-step explanation:

Calculation to determine what The equivalent units of production for the period for conversion costs were

Equivalent units of production=[$84,300+ ($50,300 * 20% ]

Equivalent units of production=$84,300+$10,060

Equivalent units of production=$94,360

Therefore The equivalent units of production for the period for conversion costs were $94,360