Answer:
Results are below.
Step-by-step explanation:
Giving the following information:
Direct materials: 5 pounds at $8.00 per pound $40.00
The planning budget for March was based on producing and selling 25,000 units.
a)
The material cost included in the planning budget is the standard cost multiplied for the budgeted production.
Direct material requiered= 25,000*5= 100,000 pounds
Standard cost per pound= $5
Direct material budget= 100,000*5= $500,000
b)
The raw material's flexible budget adapts to the actual production level.
Direct material flexible budget= standard cost*actual material used in production
Direct material flexible budget= 5*160,000
Direct material flexible budget= $800,000
c)
To calculate the direct material price variance, we need to use the following formula:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (5 - 7.5)*160,000
Direct material price variance= $400,000 unfavorable