417,787 views
7 votes
7 votes
Dream House Builders, Inc. applies overhead by linking it to direct labor. At the start of the current period, management predicts total direct labor costs of $100,000 and total overhead costs of $20,000. On January 31, the direct labor for this job equals $2,700.

Required:
Complete the journal entry.

User Kibernetik
by
2.9k points

1 Answer

7 votes
7 votes

Answer:

Date Account Title Debit Credit

January 31 Work in Process $540

Factory Overhead $540

Step-by-step explanation:

Overhead is applies by linking it to direct labor.

Overhead is $20,000 when Direct labor is $100,000.

= 20,000 / 100,000

= 20%

The overhead for this job must therefore be:

= 20% * 2,700

= $540

User Sefiks
by
2.2k points