70.9k views
3 votes
Which of the following activities does NOT belong to the controlling phase of project​ management? A. shift resources B. revise plans C. define the project D. monitor​ resources, costs,​quality, and budgets

1 Answer

6 votes

Answer: D

Explanation: Monitoring resources does NOT belong in the controlling phase of project management

User C Hogg
by
3.3k points