Answer:
B. Progress reports
Step-by-step explanation:
Since in the question it is mentioned that Jeremy who is the team leader wants to display the new product of the company at the bid convention so he would be ready on time so here the weekly report that he should be make for the team is progress report that shows the company achieved during the week and what would be achieved in the future. It also be the goal-oriented having deadlines and accurate explanation related to what has been done and what to be left
So option B is correct