Answer:
$48 U
Step-by-step explanation:
Calculation to determine what The activity variance for supplies cost in March would be closest to:
First step is to calculate the Planning supply activity cost
Planning supply activity cost = (614 × $8) +$1,740
Planning supply activity cost = 4,912+$1740
Planning supply activity cost = $6652
Second step is to calculate the Actual supply activity cost
Actual supply activity cost = (620 × $8) + $1,740
Actual supply activity cost =4960+$1,740
Actual supply activity cost =$6,700
Now let calculate the Activity variance for supplies cost using this formula
Activity variance for supplies cost = Actual activity cost – Planning activity cost
Let plug in the formula
Activity variance for supplies cost= $6,700 - $6,652
Activity variance for supplies cost= $48 Unfavorable
Therefore The activity variance for supplies cost in March would be closest to:$48 U