To compleate a task in 16 days a company needs 5 workers each working 6 hours per day

The company decides to have 8 people each working 4 hours per day
Assuming that each person works at the same rate
How many days will the task take to complete?

User Oliverpool
by
7.4k points

1 Answer

3 votes

Answer:

10 days

Explanation:

This is a type of proportion either direct or indirect .16 days for 5 workers.so for 8 workers the days will reduce .Now for 8 workers it will be 10days

User Matelutex