250,984 views
5 votes
5 votes
Which statement is true of Critical Path Method (CPM)?

a. Activities on the critical path take the shortest time to be completed.
b. A delay in the activities of a project does not affect the scheduled delivery of the project.
c. Activities that are on the critical path are flexible and can be delayed without delaying a project.
d. It determines the critical path for the completion of a series of interrelated activities.

User PJCHENder
by
3.0k points

1 Answer

26 votes
26 votes

Answer:

d. It determines the critical path for the completion of a series of interrelated activities.

Step-by-step explanation:

The Critical Path method is a method to lay out the different steps or interrelated activities of a project, in a graphical manner, that shows the interrelations, the time each activity takes to complete, the different alternatives or paths for project completion, and the total completion time for the project.

It also shows the amount of time a delay in one of the activities would delay the project as a whole.

User Samuli Asmala
by
3.1k points