Answer:
$26,000 adverse variance
Step-by-step explanation:
Fixed Overheads Volume Variance = Budgeted Overheads at Actual Output - Budgeted Fixed Overheads
= $1.30 x 60,000 hours - $1.30 x 80,000
= $78,000 - $104,000
= $26,000 adverse variance
The fixed factory overhead volume variance is $26,000 adverse variance