Marigold Corp. enters into a contract with a customer to build an apartment building for $1,069,900. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $153,300 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $51,100 each week that completion is delayed. Marigold commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability August 1, 2021 70 % August 8, 2021 20 August 15, 2021 6 After August 15, 2021 4 Determine the transaction price for this contract.

User Mikelikespie
by
2.7k points

1 Answer

13 votes
13 votes

Answer:

$1,193,562

Step-by-step explanation:

Calculation to Determine the transaction price for this contract.

First step is to calculate the probabilities

Probabilities

August 1, 2021 =70 % *$153,300

August 1, 2021 =$107,310

August 8, 2021= 20%*$51,100

August 8, 2021= $10,220

August 15, 2021 =6%*$102,200

($153,300-$51,100)

August 15, 2021 =$6,132

After August 15, 2021= 4%*$0

After August 15, 2021= $0

Now let calculate the transaction price for this contract.

Total transaction price =$1,069,900+ $107,310+$10,220+$6,132+$0

Total transaction price =$1,193,562

Therefore the transaction price for this contract will be $1,193,562