235,475 views
38 votes
38 votes
250 hours are required to complete a project .6 men are employed for this project.The hourly rate of each man is $ 7.30.If the 6 men do not work overtime, find the total amount to be paid to the men.

User Asgs
by
2.6k points

1 Answer

26 votes
26 votes

Answer:

$1,825

Explanation:

The computation of the total amount paid to the men is shown below:

Since 250 hours are needed to finish a project

and 6 men are employed

So each men worked for

= 250 ÷ 6

= 41.67 hours

And, the hourly rate is $7.30

So each man paid is

= 41.67 hours × $7.30

= $304.191

ANd, there is 6 men

So the total amount would be

= $304.191 × 6

= $1,825

User Martynas
by
3.4k points