14 votes
Kinetic Company estimates that overhead costs for the next year will be $1,600,000 for indirect labor and $400,000 for factory utilities. The company uses direct labor hours as its overhead allocation base, and plans to use 50,000 direct labor hours for this next year. If a product uses 5 direct labor hours, then it will be assigned $200 in overhead costs.a. True

b. False

User Lakmal Vithanage
by
2.8k points

1 Answer

19 votes
19 votes

Answer:

The correct answer is "False".

Step-by-step explanation:

The given values are:

Indirect labor,

= $1,600,000

Factory utilities,

= $400,000

Direct labor hours,

= $50,000

Now,

The plantwide overhead rate will be:

=
(Indirect \ labor +Factory \ utilities)/(Direct \ labor \ hours)

On substituting the values, we get

=
(1,600,000+400,000)/(50,000)

=
(2,000,000)/(50,000)

=
40 ($) direct labor per hour