Answer:
The single plantwide overhead rate= $4.94
Step-by-step explanation:
The single factory wide overhead absorption rate is that which is used to charge overhead to different product units. The amount to be charged to units would depend on the number of processing hours required
The single plantwide overhead rate = Budgeted overhead/Budgeted processing hours
= 61,776/12,500=$4.94 per hour
The single plantwide overhead rate= $4.94