361,353 views
41 votes
41 votes
Marquis Company estimates that annual manufacturing overhead costs will be $900,000. Estimated annual operating activity bases are direct labor cost $500,000, direct labor hours 50,000, and machine hours 100,000.Compute the predetermined overhead rate for each activity base. (Round answers to 2 decimal places, e.g. 10.50% or 10.50.)Overhead rate per direct labor cost _____ %Overhead rate per direct labor hour $ _____Overhead rate per machine hours $ _____

User Mirzhan Irkegulov
by
3.1k points

1 Answer

13 votes
13 votes

Answer:

$18.00

Step-by-step explanation:

Overhead rate = Estimated Overheads ÷ Estimated Activity

= $900,000 ÷ 50,000

= $18.00

Therefore,

Overhead rate per direct labor hour is $18.00

User Aleksei Zabrodskii
by
2.9k points