The balance on the job cost sheets for each job will be:
Job 765:
Direct materials = $6160
Direct labor = $1848
Overhead cost = 22 × $107 = $2354
Total job cost = $6160 + $1848 + $2354 = $10362
Job 766:
Direct materials = $13338
Direct labor = $4212
Overhead cost = 78 × $107 = $8346
Total job cost = $13338 + $4212 + $8346 = $25896