At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information:Job Direct Materials Direct Labor Machine HoursJob 765 $6,160 $1,848 22Job 766 13,338 4,212 78Job 765 produced 132 units, and Job 766 consisted of 234 units.Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $107 per hour.a. Determine the balance on the job cost sheets for each job.

User Koraytaylan
by
2.2k points

1 Answer

19 votes
19 votes

Answer: See explanation

Step-by-step explanation:

The balance on the job cost sheets for each job will be:

Job 765:

Direct materials = $6160

Direct labor = $1848

Overhead cost = 22 × $107 = $2354

Total job cost = $6160 + $1848 + $2354 = $10362

Job 766:

Direct materials = $13338

Direct labor = $4212

Overhead cost = 78 × $107 = $8346

Total job cost = $13338 + $4212 + $8346 = $25896