Answer:
$23,595
Step-by-step explanation:
The computation of the direct labor in the planning budget is shown below:
Direct labor in planning budget is
= Actual level of Activity × Direct labor per unit
= 6,050 × $3.90
= $23,595
For calculating the direct labor in the planning budget we simply multiplied the actual activity level by the direct labor per unit
This is the answer but the same is not provided in the given options