205k views
2 votes
A bucket begins weighing 20 pounds, including the sand it holds. The bucket is to be lifted to the top of a 25 foot tall building by a rope of negligible weight. However, the bucket has a hole in it, and leaks 0.1 pounds of sand each foot it is lifted. Find the work done lifting the bucket to the top of the building

User SaxonMatt
by
5.5k points

1 Answer

5 votes

ANSWER


\begin{equation*} 468.75\text{ foot-pound} \end{equation*}

Step-by-step explanation

Let the bucket be lifted x feet.

The weight of the bucket at x feet is given by:


20-0.1x

The work done in lifting the bucket by dx feet is:


dW=(20-0.1x)dx

The total work done is the integral of the work done in lifting the bucket x feet, that is:


W=\int(20-0.1x)dx

Hence, the work done in lifting the bucket 25feet is:


\begin{gathered} W=\int_0^(25)(20-0.1x)dx \\ \\ W=(20x-(0.1x^2)/(2))_0^(25) \\ \\ W=(20*25-(0.1*25^2)/(2))-(20*0-(0.1*0^2)/(2)) \\ \\ W=500-31.25 \\ \\ W=468.75\text{ foot-pound} \end{gathered}

That is the answer.

User Davka
by
5.2k points