Answer: 0 units
Step-by-step explanation:
Future Planned Production Orders = Expected goods requirement - Finished goods in inventory - Schedule production
= 550 - 450 - 150
= -50 units
Include no units because the finished goods and the scheduled production make up the requirement for the period.