How might a Product Owner (PO) adjust team events to take advantage of this capability and promote the flow of value?

User Richard
by
2.9k points

1 Answer

24 votes
24 votes

Answer:

hello your question is incomplete below is the complete question

An Agile Release Train (ART) has implemented a completely automated Continuous Integration/Continuous Delivery (CI/CD) pipeline that can deploy code as it is checked into the source-code repository. How might a Product Owner (PO) adjust team events to take advantage of this capability and promote the flow of value? 1. Release Stories that have been included in the team demo 2. Review and accept Stories as they are completed 3. Identify Stories that are cleared for automatic delivery during Iteration Planning 4. Implement Feature toggles to control which Stories are released

answer : Identify Stories that are cleared for automatic delivery during Iteration Planning ( 3 )

Step-by-step explanation:

The Best way a product owner( PO ) can adjust team events in order to take advantage of this capability and promote the flow of values is ; Identify Stories that are cleared for automatic delivery during Iteration Planning.

This is because this options identifies ART and its clearance.