The first machine can produce 2,100 shirts in 140 min, then the shirts per minute it can produce is:

The second machine can produce 2,400 shirts in 120 min, then it can produce in one minute:

If the two machines work together, they can produce 15+20=35 shirts per minute, then to produce 7,350 shirts it will take:

The answer is 210 minutes.