Ruthanna is the project manager of the HGB project for her organization. This project is a remodeling of a client's dentist office. Ruthanna and the project team have identified several tasks which can happen in any order. For example, the team could install the new light fixtures before or after the carpet is installed. What term is given to activities that have this type of dependency

User Ed Mozley
by
2.3k points

1 Answer

10 votes
10 votes

Answer:

Discretionary

Step-by-step explanation:

Discretionary

User Changbin Du