Answer:
$3,283
Step-by-step explanation:
Calculation for the overhead cost be added to Job W at year-end
Using this formula
Overhead cost =(Overhead cost / Direct Labor) *Job W Direct Labor
Overhead cost=($6,365 / $9,500) *$4,900
Overhead cost=0.67*$4,900
Overhead cost=$3,283
Therefore the overhead cost be added to Job W at year-end is $3,283