Write an equation of variation to represent the situation and solve for the missing information The time to complete a project varies inversely with the number of employees. If 3 peoplecan complete the project in 7 days, how long will it take 5 people?

1 Answer

4 votes

the relation between the days and number of employee is inverse relation,

so,


D\propto(1)/(n)

here D = days,

n = no. of employees.


D=(k)/(n)

put D = 3 and n = 7


\begin{gathered} 3=(k)/(7) \\ k=21 \end{gathered}

so for n = 5


\begin{gathered} D=(k)/(5) \\ D=(21)/(5) \\ D=4.2\text{ days} \end{gathered}

it will take 4.2 days if 5 people do it.