If 10 man can work 6hours.How many more men are needed towork in 4 hours​

User Maria Jane
by
3.3k points

1 Answer

27 votes
27 votes

Answer:

5 more men

Explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.