When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 72 days by 5 workers. How many days would it take to build a similar house with 18 workers.

User Aynsley
by
8.2k points

1 Answer

2 votes

Let the number of day is expressed as d and number of workers as w.

So relation between number of workers and number of days is,


\begin{gathered} n\propto(1)/(w) \\ n=k(1)/(w) \\ n=(k)/(w) \end{gathered}

Substitute 72 for d and 5 for w in the equation to obtain the value of k.


\begin{gathered} 72=(k)/(5) \\ k=72\cdot5 \\ =360 \end{gathered}

The equation is,


n=(360)/(w)

Substitute 18 for w to determne the number of day.


\begin{gathered} n=(360)/(18) \\ =20 \end{gathered}

So 20 days are required to build a house with 18 workers.

Answer is 20 days.

User Jorge Candeias
by
7.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories