What is changing per day in road length?What is road length when crew started working

What is changing per day in road length?What is road length when crew started working-example-1
User Tal Barda
by
5.6k points

1 Answer

5 votes

Given the equation


y=2x+51

Notice that it is a linear equation

The change per day in the road's length is given by the slope of the line which is the constant that accompanies the x-term.

Therefore, the answer to part 1) is 2 miles.

On the other hand, set x=0 (zero days since the crew started working); then,


\begin{gathered} y=2\cdot0+51 \\ \Rightarrow y=51 \end{gathered}

Thus, the initial length of the road is 51 miles.