Due to delays, a company had to extend a project from 26 days to 42

days. What was the percentage increase in time to complete the
project? Round your answer to the nearest tenth.

User Adrian Marinica
by
3.1k points

1 Answer

4 votes
4 votes

Answer:

It should be 38.1