f(x)=4.1x+1.9

where x is the number of days since the start of the job

and f(x) is the rate of change

Step 1

a)find the total expenditure if the job takes 12 days

so, as x represents the number of days, just replace and calculate

let x= 12


\begin{gathered} f(x)=4.1x+1.9 \\ f(12)=4.1(12)+1.9 \\ f(12)=49.2+1.9 \\ f(12)=51.1 \end{gathered}

so

a) 51.1

Step 2

now, let's find the total spent on the job from the 10 to 20th day

a) find the x value ( number of days since the job started)

x= 20 days-10dys= 10

so

x= 10

User Vivek Patel
by
7.9k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories