Answer:
Workers to be be added to finish the work in 24 hours = 348
Explanation:
This is a problem involving inverse proportion
Here the number of days required to complete the job is inversely proportional to the number of workers- the more the workers, the less time it takes
We can state this as:
where D = time in days required to complete the job and N is the number of workers that can do this in D days
The equation relating D and N can be stated as
This gives us k = D x N (multiply by N both sides)
where k is a constant known as the constant of proportionality
Given data that D = 30 when N = 12, this constant of proportionality = D x N = 30 x 12 = 360
From the equation of proportionality we also get
N = k/D
So to complete the job in 24 hours = 1 day, substitute 1 for D and 360 for k to get
N = 360/1 = 360 workers
So you will need 360-12 = 348 workers if you expect to finish the job in 24 hours = 1 day