Given :-
- 12 workers can do a piece of work in 20 days .
To Find :-
- How many workers should be added to complete the work in 16 days ?
Solution :-
According to the question ,
→ In 20days 12 workers can do a piece of work.
→ In 1day 12*20 workers can do that work
( Less days , more workers )
→ In 16 days 12*20/16 = 15 workers can do the work.
So 15 -12 = 3 workers should be added to complete the work.
Hence the required answer is 3 .