There are 15 floors of an office building each floor is 10 2/5 feet tall 24 9/10 feet of the building are completed 1 1/4 feet of the building can be finished each day how many days are needed to complete the building

User H Q
by
4.0k points

2 Answers

5 votes

Answer:

104.88 (rounded 105)

Explanation:

The total height of the building is 156'. I got that by multiplying 10.4 by 15.

Then I made an equation.

156 = 1.25x + 24.9

-24.9 -24.9

131.1 = 1.25x

/1.25 /1.25

104.88 = x

x represents the number of days.

So it will take 104.88 days or if your teacher wants you to round, it will take 105 days to finish the building.

User Farruh Habibullaev
by
4.1k points
5 votes
If there are 15 floor and each one is 10 2/5 tall then multiply that together to get 156. Then subtract 24 9/10 from that because that has already been completed to get 131 1/10. Then divide 1 1/4 by 131 1/10 to get 104 22/25.