Answer: 8 spools
Explanation:
There are 12 apartments, and each apartment will need 60 meters of cable, so 12×60= 720 meters of cable needed.
If each spool only has 100 meters and he needs 720 meters, then 720÷100= 7.2. So he would need to purchase at least 8 spools, and will have 80 meters left over.