A construction company will be penalized each day of delay in construction for bridge. The penalty will be $4000 for the first day and will increase by $1000 for each following day. Let f(n) be the amount
asked
Nov 9, 2023
125k
views
3
votes
A construction company will be penalized each day of delay in construction for bridge. The penalty will be $4000 for the first day and will increase by $1000 for each following day. Let f(n) be the amount penalized for the nth day. How much will the company owe if they are delayed 12 days?
Mathematics
college
Shryme
asked
by
Shryme
8.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
6
votes
Answer:
15,000 total, 4000 day 1, then 1000 for day 2 thru 12.
Dieworld
answered
Nov 16, 2023
by
Dieworld
7.4k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.8m
questions
11.4m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
A dealer sells a certain type of chair and a table for $40. He also sells the same sort of table and a desk for $83 or a chair and a desk for $77. Find the price of a chair, table, and of a desk.
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org