The detailed plan that shows the exact end items (i.e., finished products) to be produced in a specific time frame is known as what

User Elyas
by
2.6k points

1 Answer

21 votes
21 votes

Answer:

Master Production Schedule (MPS)

Step-by-step explanation:

Master production schedules are plans for individual products to be produced. The plans specify the time a specific product is produced, inventory needs, staffing needs, etc. A master production schedule or MPS will quantify raw materials, processes, and other resources needed to optimize production. (optessa.com)