The graph below shows a line of best fit for the number of workers needed for different construction projects.

The equation for the line of best fit is shown below.



Based on the line of best fit, what is the expected time for completion with 14 workers on the project?
A.
7.5 days
B.
8.5 days
C.
12 days
D.
10 days

The graph below shows a line of best fit for the number of workers needed for different-example-1
User Yulia Rogovaya
by
2.6k points

1 Answer

23 votes
23 votes

Answer:

D. 10