Final answer:
The materials price variance is $1,800 favorable, indicating the actual price paid per plate is less than the standard cost. The materials quantity variance is $5,250 unfavorable because more plates were used than the standard required for the tests performed.
Step-by-step explanation:
To calculate the materials price variance for the plates, we need to know the standard cost per plate and the actual cost per plate. The standard cost is $2.50 per plate, as given in the industry averages. The hospital, however, paid $28,200 for 12,000 plates, which means they paid $2.35 each after the 6% discount. Hence, the materials price variance is:
- (Standard Price - Actual Price) x Actual Quantity
- (2.50 - 2.35) x 12,000 plates
- $0.15 x 12,000 plates = $1,800 favorable
The materials quantity variance looks at the amount of plates used versus what should have been used. Since two plates are required per test, the standard quantity of plates needed for 1,800 blood tests and 2,400 smears is (1,800 tests + 2,400 tests) x 2 plates/test = 8,400 plates. We know that 12,000 plates were purchased and 1,500 remained, meaning 10,500 were used. The materials quantity variance is:
- (Standard Quantity - Actual Quantity) x Standard Price
- (8,400 plates - 10,500 plates) x $2.50
- -2,100 plates x $2.50 = $5,250 unfavorable
This indicates the hospital used more plates than the standard, therefore incurring additional costs.