Suppose that 5 workers can complete a certain task in 12 days. If there are 4 workers, how many days would it take for them to finish the same task

1 Answer

3 votes

Answer:

15 days

Explanation:

5 workers times 12 days is 60 days per worker which gets reduced based on how many workers there are. 60 divide by 4 workers now brings down to 15 days. 5 workers, 12 days. 10 workers 6 days etc.