5. If 15 men can finish a work in 16 days in how many days will 8 men can finish the same work? a. 15 b. 20 c. 30 d. 42​

User Adamretter
by
5.6k points

2 Answers

3 votes

Answer:

Option c.

Explanation:

It is an inverse proportion, fewer workers more days to finish the job.

15 -----16

8 ----- x

x = (16)(15)/8 = 240/8 = 30 days

Hope this helps

User Teabot
by
5.1k points
3 votes

Answer:

C. 30

Explanation:

15 men do work in 16 days

This means that 7.5 men (15/2) would do that same work in 32 days (16x2).

If the number of men increase, the amount of days decrease.

8 men would do that work in 30 days

8 men > 7.5 men

30 days < 32 days

User Manji
by