An employee worked for 8 hours on 2 days, 6 hours on 1 day, and 4 hours on 2 day

What is the average number of hours the employee worked per day?
A.) 6.0
B.) 6.5
C.) 7.0
D.) 7.5
E.) 8.0

User Saravankg
by
8.3k points

1 Answer

4 votes

Answer:

A) 6.0

Explanation:

First, total amount of hours, since average is sum of the numbers by how many numbers there is.

Day 1=8x2 hr

Day 2=6x1 hr

Day 3=4x2 hr

which is, 16+6+8=30

then divide 30 by how many days there is, which is 5 days.

30/5=6