98.6k views
0 votes
30men can do a piece of work in 40 days how long will it take to complete the work by 25 men

User Ferrard
by
4.5k points

1 Answer

3 votes

Explanation:

men × days=men1×days1

30×40=40×x

x=30days

User LaGrandMere
by
4.2k points