Answer:
a) ≈ 30 mins
b) 8 vpm
Step-by-step explanation:
a) Determine how long after the first vehicle arrival will the queue dissipate
The time after the arrival of the first vehicle for the queue to dissipate
= 29.9 mins ≈ 30 mins
b) Determine the average service rate at the parking lot gate
U = A / t
where : A = 240 vehicles , t = 30
U = 240 / 30 = 8 Vpm
attached below is a detailed solution of the given problems above