Answer:
B. $2,228,000 underapplied
Step-by-step explanation:
Calculation for the what the overhead
First step is to calculate the Predetermined Overhead rate
Using this formula
Predetermined Overhead rate
= Budgeted Overhead Expense ÷ Budgeted Machine Hours
Let plug in the formula
Predetermined Overhead rate
= $11,506,000 ÷ 165,000
Predetermined Overhead rate= 70 per machine hour
Second step is to calculate the Allocated MOH using this formula
Allocated MOH = Actual machine hours × Predetermined Overhead rate
Let plug in the formula
Overhead applied= 81,000 hours × 70 per machine hour
Overhead applied= $5,670,000
Now let calculate Overhead Underapplied using this formula
Overhead Underapplied= Actual overhead - Allocated MOH
Let plug in the formula
Overhead Underapplied= $7,898,000 - $5,652,180
Overhead Underapplied= $2,228,000
Therefore the Overhead is $2,228,000 underapplied