how many machines will be needed to complete a task in 18 days, given that it takes 12 days for 6 machines to complete the same task ?
asked
Sep 10, 2023
1.5k
views
18
votes
how many machines will be needed to complete a task in 18 days, given that it takes 12 days for 6 machines to complete the same task ?
Mathematics
high-school
Bojan Radivojevic
asked
by
Bojan Radivojevic
4.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
10
votes
Answer:
9 days
Explanation:
Rosael
answered
Sep 16, 2023
by
Rosael
4.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
4.5m
questions
5.9m
answers
Other Questions
Before beginning voice lessons, Aubrey already knew how to sing 357 pieces, and she expects to learn 2 new pieces during each week of lessons. After 78 weeks of voice lessons, how many pieces will Aubrey
A study was completed in Florida. In southern Florida, the study involved 3,000 patients; 54% of them experienced flulike symptoms during the same month. The study had a margin of error of 1.8%. What does
3x-by=-3 b=? what is the number of b?
Please answer asap.......... ...
Can someone help me plz I have to Turn 27/9 in simplest
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org